Halifax Beech Hill

This project is to assist with the demolition of three high-rise tower blocks and Stannary Depot with a view to developing the delivery of new housing development in its place. The funding will principally focus on Phase 1 of the regeneration project; this will include the construction of 114 homes, of which 50% will be affordable.

Beech Hill lies on the Western edge of Halifax Town Centre. In conjunction with the LEP, the regeneration of the site is a joint venture partnership with Calderdale Metropolitan Borough Council and Together Housing Group (THG) who owned the three demolished tower blocks that used to occupy the site, which includes the Council's old Stannary Depot. This has now concluded the Phase 1a project. The cleared site is now being progressed for the delivery of new housing. 

Homes England are match funders through the Estates Regeneration Fund.

The Phase 1b project to deliver this housing is currently being defined and will include the construction of up to 114 homes, the vast majority of which will be affordable or social rented homes. 

Project Lead

Calderdale Council

Business case summary

Link here

Funding

Growth Deal £2.197 million

Project Status

Phase 1a- Activity 6: Delivery

Phase 1b- Activity 5: Full Business Case with Finalised costs

Start and end dates

Phase 1a: 2017- 2019

Phase 1b: To be confirmed 

Delivery partners

West Yorkshire Combined Authority

Together Housing

Other funders

Together Housing- £15.2 million

Homes England- £2.1 million

Get in touch (contact information)

 