Road improvements
Road and highway improvement projects which are part of West Yorkshire-plus Transport Fund.
Projects within this area
Browse the different projects within this area by opening and closing the tabs below.
- A6110 Leeds Outer Ring Road
-
Project overview
The A6110 forms the South West corner of the Leeds Outer Ring Road and is the busiest section in terms of vehicle numbers. Congestion is evident on a daily basis particularly at the junctions with the key radial A58 (Whitehall Road) and A62 (Gelderd Road) routes.
The scheme includes improvements to a number of junctions on the route between the Stanningley By-pass in the North, to the interface with the Mirfield to Dewsbury to Leeds (M2D2L) scheme. The actual boundary between the two proposals will be on the South East side of the M621 (junction 1).
Key aims
- To provide safe crossing and cycling facilities to encourage more people to travel be active transport for both work and leisure.
- To reduce adverse impacts of transport on the environment and health by promoting active travel. opportunities, helping to contribute towards net-zero carbon emissions by 2030.
- To better manage congestion and reduce traffic delays through upgraded signals and adaptive traffic management making the corridor an easier place to travel through and link with surrounding areas.
- To enhance public transport by providing bus priority infrastructure to improve journey time reliability and increase bus patronage.
- To facilitate and support growth in employment, housing and economic development in areas like Beeston, Cottingley, Morley and Wortley and across Leeds City Region.
- To improve the quality of the local environment and public realm to support regenerations along the route.
- Reduce congestion and journey times along the A6110 corridor.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund- £3 million
CRSTS- £4 million
Project Status Activity 4 - Full Business Case Start and end dates 2025 - 2027 Delivery partners Leeds City Council Other funders S106 £1.5m Get in touch connectingleeds@leeds.gov.uk Last updated in February 2024
- A62 Cooper Bridge Improvement
-
Project overview
Cooper Bridge junction is where the A62, one of the main transport routes into and out of Huddersfield and on to Leeds and the A644 link to the M62 meet, making it one of the most important gateways into the town.
This scheme involves highway improvements, road widening and junction upgrades to relieve the severe congestion that develops in the Cooper Bridge area, particularly during the morning and evening peak. It would also provide the additional capacity that would make local housing and employment growth possible as well as improving air quality.
Project Lead Kirklees Council District/ Area Kirklees Funding West Yorkshire plus Transport Fund- £75.1 million Project Status Activity 3: Outline Business Case Start and end dates September 2026 - August 2029 Delivery partners West Yorkshire Combined Authority Other funders None Get in touch major.transport@kirklees.gov.uk Last updated September 2023
- A629 Improvements Programme
-
Project overview
Our £120m investment into the A629 between Halifax, in Calderdale, and Huddersfield, in Kirklees, will help reduce congestion, improve journey times, boost public transport use and improve cycling and walking conditions.
The works are being funded through the West Yorkshire-plus Transport Fund. In addition to highway improvements, Halifax town centre will also benefit from a new bus and rail interchange, remodelled bus station, new bus routing and improved quality public areas.
There are six separate phases of work within the scheme.
A629 Phase 1a Salterhebble to Shaw Hill
The scheme, which consisted of improvements to the A629 between Jubilee Road and the Free School Lane junction to the south of Halifax town centre was part of the wider A629 Halifax to Huddersfield Corridor Improvements programme funded through the West Yorkshire plus Transport Fund (WY+TF).
The scheme received decision point 5 approval in June 2017 with construction being completed in November 2018 and outstanding snagging works in November 2019.
Project objectives:
- Accessibility improved to and from Halifax, Huddersfield and key employment areas and between surrounding business and residential areas;
- Increased cycle mode share to key attractors and improved pedestrian infrastructure on the A629 corridor;
- Reduced journey times and levels of delay and queuing on the A629 for all modes including a decrease in public transport journey time variability;
- Improved environment via green infrastructure.
All of the scheme objectives have been met with the funding used for the below activities:
- Consultant / internal staff resourcing;
- Traffic modelling / optioneering;
- Preliminary and Detail Design;
- Consultation
- Mandate / Outline / Full Business Case;
- Land acquisition / legal fees;
- Monitoring and Evaluation;
- Construction tendering;
- Construction supervision;
- Utility diversions;
- Construction works;
- Project closure
Latest News
Project Lead Calderdale Council District/ Area Calderdale Funding £8.5 million West Yorkshire-plus Transport Fund Project Status Activity 6: Project Closure Start and end dates Completed November 2018 Delivery partners Jackson Civils Other funders None Get in touch Thenextchapter@calderdale.gov.uk Last updated September 2023
A629 Phase 1b Calder and Hebble Junction
The A629 Phase 1b will deliver improvements to the A629 corridor between Ainley Top roundabout junction with Jubilee Road. The primary focus is targeting the current network pinch point of the Calder & Hebble junction.
Project Lead Calderdale Council District/ Area Calderdale Funding West Yorkshire + Transport Fund - £36,619,000 Project Status Activity 5: Delivery Start and end dates 2020-2024 Delivery partners Calderdale Council Other funders None Get in touch Thenextchapter@calderdale.gov.uk
https://calderdalenextchapter.co.uk/projects/a629-calder-and-hebble-junction
Last updated September 2023
A629 Phase 2 Halifax Town Centre
The town centre of Halifax will be improved through pedestrianisation of key shopping areas and creation of new public realm at ‘Piece Gardens’, adjacent to the Square Chapel and Central Library. This will create a cultural quarter from the rail station into the town centre.
This major investment project will make Halifax a place where people want to live, work and study, and will attract investment from a whole range of sectors.
Project Lead Calderdale Council District/ Area Calderdale Funding West Yorkshire + Transport Fund - £53,340,000 Project Status Activity 4: Full Business Case Start and end dates 2024 - 2028 Delivery partners West Yorkshire Combined Authority. Calderdale Council Other funders None Get in touch Thenextchapter@calderdale.gov.uk
https://calderdalenextchapter.co.uk/projects/a629-halifax-town-centre
Last updated September 2023
A629 Phase 4 Halifax to Huddersfield
The £120m package of schemes along the A629 corridor between Halifax and Huddersfield is driving economic growth by addressing transport and accessibility issues.
The project complements the work of the other stages of the A629 improvement scheme being delivered by Calderdale and Kirklees Councils, by improving walking, cycling and bus travel along the corridor. The improvements will also enable local growth and reduce journey times.
Plans include the creation of a quality bus corridor, with improved bus stops and real time information, creating the opportunity for bus operators to introduce an express service between Huddersfield and Halifax. Junction improvements will also reduce congestion and increase capacity at Ainley Top and West Vale.
Cycling and walking opportunities will also be transformed, with new and improved routes, and better links to key destinations, such as hospitals, Halifax and Elland rail stations, and Elland, Huddersfield and Halifax town centres. These routes will include off-highway green routes and on highway cycle infrastructure.
Project Lead Calderdale Council District/ Area Calderdale / Kirklees Funding West Yorkshire + Transport Fund - £25,928,000 Project Status Activity 3: Outline Business Case Start and end dates Scheme has been pipelined following the November 2022 inflation review. Delivery partners West Yorkshire Combined Authority, Calderdale Council Other funders None Get in touch Thenextchapter@calderdale.gov.uk Last updated September 2023
A629 Phase 5 Ainley Top to Huddersfield
This £120m package of schemes along the A629 corridor between Halifax and Huddersfield is designed to speed up public transport and car journeys along the route, unlock key development sites and deliver improved facilities for cycling and walking.
Planned measures include highway widening, remodelling junctions and signals, improved public transport including a new bus rail interchange and new cycling and walking infrastructure.
Phase 5 of the scheme will see measures to reduce congestion and speed up journey times for all A629 users between Huddersfield ring road and Ainley Top roundabout.
The A629 Halifax to Huddersfield Corridor Improvement is the largest individual scheme within the West Yorkshire-plus Transport Fund.
Project Lead Kirklees Council District/ Area Kirklees Funding West Yorkshire plus Transport Fund - £10.5 million Project Status Activity 4: Full Business Case Start and end dates May 2024 - May 2025 Delivery partners West Yorkshire Combined Authority Other funders Kirklees Council - £837k Get in touch major.transport@kirklees.gov.uk Last updated September 2023
- A650 Hard Ings Road Improvements, Keighley
-
Project overview
Local people will enjoy the benefits of new, segregated cycle and pedestrian routes along the southern side of Hard Ings Road and a new toucan crossing at Lawkholme Lane to Royd Way tying into the existing cycle route on Royd Ings Avenue.
Where possible, new native trees will be planted along the roadside and verge areas and any trees needing to be removed for road widening will be replaced with trees either as part of the scheme or nearby. Landscaped areas affected by the construction works will be replanted and the embankment at the cricket ground cleared and replaced with new shrubs and trees.
This scheme completed in November 2020 and was awarded the Best New Infrastructure Project in the Yorkshire and Humber at the Chartered Institute of Highways and Transportations awards.
Project Lead Bradford Council District/ Area Bradford Funding West Yorkshire-plus Transport Fund £9.334 million Project Status Activity 6: Project Closure Report Start and end dates May 2019 - November 2020 Delivery partners Bradford City Council and Howard Civil Engineering Other funders None Get in touch Email the West Yorkshire Combined Authority Last updated September 2023
- A650 Tong Street
-
Project overview
The current vehicle capacity on the A650 causes congestion and results in significant levels of traffic through residential areas, presenting a key pinch point in the road network.
This scheme is likely to comprise of highway capacity, efficiency, safety and air quality improvements along with enhancements to pedestrian and cycle provisions.
Project Lead Bradford Council District/ Area Bradford Funding West Yorkshire Combined Authority - £4 million Project Status >Activity 3: Outline Business Case Start and end dates Scheme is being pipelined at the Full Business Case stage following the November 2022 inflation review Delivery partners Bradford Council Other funders Potential DfT funding Get in touch Email the West Yorkshire Combined Authority
Last updated in September 2023
- CityConnect Phase 3
-
Project overview
Phase 3 of the West Yorkshire Combined Authority's CityConnect programme is made up of 8 schemes, 4 of which are complete, and includes a mixture of on and off-highway schemes across West Yorkshire and York. These schemes link in with previous CityConnect phases to further expand the cycling and walking network within West Yorkshire and York.
Project Lead West Yorkshire Combined Authority District/ Area West Yorkshire & North Yorkshire Funding WYTF - £12 million
Bradley to Brighouse scheme has been reduced to £700k following 2022 inflation review.Huddersfield Town Centre has been reduced to £180k following 2022 inflation review.
Getting Building Fund £500k
Project Status
Delivery of Phase 4 of the Castleford-Wakefield Greenway scheme is now complete and operational, delivering a new 1.3km of the traffic-free walking and cycling route.
Delivery of Leeds City Centre schemes on Clay Pit Lane, Elland Road and Dewsbury Road are complete and operational, adding nearly 5km of segregated cycling routes in key locations across the city.
Towpath improvements along Huddersfield Narrow Canal and Leeds Liverpool (between Shipley and Apperley Bridge) are now open and operational as of July and September 2022 respectively. These add 7.8km of upgraded canal towpath for cycling and walking.
Other schemes in Kirklees including Huddersfield Town Centre and Bradley to Brighouse Greenway have been pipelined following the November 2022 inflation review.
One scheme in York is currently in delivery.
Start and end dates 2019 - 2023 Delivery partners
Calderdale Council
Canal & River Trust
City of Bradford Metropolitan District Council
City of York Council
Kirklees Metropolitan Borough Council
Leeds City Council
SustransOther funders Leeds City Council
Kirklees Metropolitan Borough Council and City of York Council have contributed match funding.
City of York Council have secured funding from the York & North Yorkshire Local Enterprise Partnership
Get in touch/ contact information Email the West Yorkshire Combined Authority
- East Leeds Orbital Route (ELOR)
-
Project overview
The East Leeds Orbital Route scheme is a new 7km road linking the Orbital Ring Road at Red Hall to Thorpe Park. This scheme is also a key part of the East Leeds Extension to create a major strategic growth area for the city. In addition to the link road the scheme will improve a number of existing outer ring road junctions.
The scheme comprises of a new 50mph dual carriageway with pedestrian and cycle infrastructure. This scheme also includes improvements to the A6120 to the west of Red Hall Lane.
The aim of this scheme is to support the development of East Leeds Extension which is a 225ha housing development area to the East of Leeds, and a 638ha development area for employment users. This scheme will enable the development of land and reduce congestion along the Outer Ring Road.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund - £90.33 million Project Status Activity 6 - Closure and Review Start and end dates 2015 - 2022 Delivery partners Leeds City Council
Contractor – Balfour Beatty
Other funders Leeds City Council - £57.16 million Get in touch/ contact information Connectingleeds@leeds.gov.uk Last updated February 2024
- Glasshoughton Southern Link Road
-
Project overview
The Glasshoughton Southern Link Road provides a more direct route to the leisure / retail area from Wakefield and Normanton, reduces congestion and improves accessibility. It will result in a significant reduction in traffic on the A639/A6539 corridor immediately North of the Glasshoughton development area.
The additional highway capacity improves conditions for bus services (the Council has secured funding for a new bus service on this route), pedestrians and cyclists.
This scheme also enables the delivery of 1,300 new homes and creates the ability for employment opportunities due to improved connectivity.
Project Lead Wakefield Council District/ Area Wakefield Funding West Yorkshire plus Transport Fund - £5.968 million Project Status Activity 7 - Monitoring and Evaluation Start and end dates 2017 - 2022 Delivery partners Wakefield Council
Other funders Harworth Estates / Waystone Ltd dedicating land as highway Get in touch transplan@wakefield.gov.uk Last updated February 2024
- Harrogate Road New Line
-
Project overview
Both Harrogate Road and New Line are significant routes within Bradford's transport network, linking Bradford with the airport and Leeds.
Harrogate Road is a key commuter route between Bradford, Rawdon and Harrogate, as well as being the primary access between Bradford and Leeds Bradford Airport (LBA). New Line is a key route between Keighley, Shipley, Bingley and Leeds.
Extra right-turn lanes at junctions, a new P-Loop for left and right turns from Harrogate Road onto New Line, the introduction of double yellow lines and responsive traffic signals will help reduce congestion on the two routes.
Cycle lanes and wide inside lanes will enable cyclists to use the junction more safely and more comfortably and also anticipate future potential cycle routes to the railway station. Pedestrians will benefit from new islands, with controlled crossings, tactile pavement surfaces for visually impaired people, a new puffin crossing near Greengates Primary School on Harrogate Road an improved zebra crossing on New Line and new street lighting.
Bus stops will be relocated and upgraded with shelters providing real-time information and , where space permits, dedicated bus bays will be constructed, which will improve overall traffic to flow through the junction.
New trees and grass verges will increase green space around the junction and where trees need to be removed because of the scheme, new ones will be planted to replace them at other locations within the scheme and nearby.
Project Lead Bradford Council District/ Area Bradford Funding WYTF - £8.812m
City of Bradford Metropolitan Council match funding £3.016m
Private sector contributions £1.926mProject Status Activity 6: Project Closure Report Start and end dates July 20 to May 22 Delivery partners Bradford Council and Howard Civil Engineering
Other funders None Get in touch Email the West Yorkshire Combined Authority Last updated September 2023
- Leeds Bradford International Airport Link Route
-
Project overview
A new route is proposed to give more direct access to the airport from the South, linking in to the A65 North of the outer ring road.
This is intended to create better connections and maximise the role of public transport access and other sustainable travel modes to support a step change in travel behaviours and to unlock the economic benefits of the North West Leeds Employment Hub.
By improving sustainable and active travel connections in the area, the council aims to unlock investment and inclusive growth opportunities and encourage more people to walk, cycle and use public transport.
Project Lead Leeds Council District/ Area Leeds Funding West Yorkshire Plus Transport Fund- £70 million- Funding for LBA Link Route: £2,293,000 Project Status Activity 3: Outline Business Case Start and end dates Jan 2025- July 2026 Delivery partners Leeds City Council
Other funders Get in touch connectingleeds@leeds.gov.uk Last reviewed February 2024
- Leeds City Centre Package
-
Project overview
The Leeds City Centre Package is a programme of works designed to support Leeds as an Urban Growth Centre as identified in the LCR Strategic Economic Plan (SEP), delivering growth in jobs and housing on the South Bank and enabling the city to be HS2 ready.
Key objectives
- The redevelopment of City Square in line with the City of Culture ambition to allow the creation of a world class gateway for the city.
- Increase the capacity on the Inner Ring Road and M621 orbital route by reconfiguring Armley Gyratory and capacity improvements between Junctions 1 - 4 and Junction 7 M621 by 2024.
- Reduce traffic in the city centre, including the South Bank creating a quality environment attractive to development.
- Increase travel to the centre by sustainable modes of transport.
Infirmary Street Gateway
The Infirmary Street scheme will enhance a major transport gateway to Leeds city centre for bus users, pedestrians, and cycle users, through a series of bus infrastructure, public realm, pedestrian and cycling improvements.
The scheme includes Infirmary Street, Park Row and small lengths of other intersecting junctions. The improvements include the conversion of Infirmary Street (which is currently one-way eastbound) to two-way operation for buses and hackney carriages only. Park Row is to become one-way south-bound operation for buses and hackney carriages only with one running lane and the reallocation of bus bays. This will narrow the carriageway along Park Row, creating wider footways in areas with high pedestrian footfall and creating space for a segregated cycle facility on the northern side of the carriageway.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund- £8.9 million Project Status Activity 6 - Closure and Review
Start and end dates 2017 - 2021 Delivery partners West Yorkshire Combined Authority Other funders None Get in touch
Last updated February 2024
Armley Gyratory
The Armley Gyratory scheme brings together a package of interventions to reconfigure the highway network at the gyratory junction and associated routes.
Scheme delivery is anticipated to increase the capacity on the Leeds Inner Ring Road and M621 orbital route and capacity improvements between Junctions 1 - 4 and Junction 7 M621. As a result, this will reduce through-traffic in the city centre, including the South Bank, creating a quality environment attractive to development. The scheme will also encourage walking and cycling.
The Armley Gyratory is a key junction on the Inner Ring Road to the west of Leeds city centre. It is a major entry/exit point for traffic travelling through and into the city with an estimated 100,000 vehicles passing through it daily (pre Covid-19).
After two rounds of public consultation the designs have evolved, with feedback being used to understand the features that are most important to local people, which have been retained and enhanced in the new design. The updated designs will:
- Provide more appealing and accessible routes for both cyclists and pedestrians;
- Improve safety for all road users;
- Allow traffic to flow more freely, minimising traffic impacts on local roads;
- Improve the local environment through new landscaping; and
- Help facilitate improvements elsewhere in the city, including no through traffic at City Square.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund- £41.97 million Project Status
Activity 5 - Delivery
Start and end dates 2018- 2024 Delivery partners
Leeds City Council
Other funders None Get in touch connectingleeds@leeds.gov.uk Last updated February 2024
Meadow Lane (Corn Exchange Gateway)
This scheme is to deliver a series of improvements to bus infrastructure, public realm, pedestrian infrastructure and cycling infrastructure on a number of roads surrounding the Corn Exchange and taking in Vicar Lane, New Market Street, Kirkgate, New York Street, Harper Street, Kirkgate York Street, Cross York Street, Duncan Street, Call Lane, Boar Lane, Lower Briggate, Bridge End and Meadow Lane.
Meadow Lane will be transformed to contribute to Leeds City Council’s vision to produce a City Park. Continuing from Bridge End, the pedestrian and cycleway focus remains. There will be provision of protected two-way cycleway along Meadow Lane between Bridge End and Great Wilson Street and a new toucan crossing adjacent to the proposed location of City Park.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund- £9.5 million Project Status
Activity 6 - Closure and Review
Start and end dates 2018- 2022 Delivery partners West Yorkshire Combined Authority Other funders None Get in touch connectingleeds@leeds.gov.uk Last updated February 2024
City Square Plus
Closure of City Square to traffic from 2023 plus a series of small complementary schemes to be developed and implemented as a result of the closure of City Square in a combined package called City Square Plus.
A key component of this scheme is the closure of City Square to general traffic from January 2023 to allow the creation of a world class gateway for the city. A series of smaller complementary schemes which are intended to support the closure of City Square, have been grouped with City Square into a single scheme known as City Square+, which includes East Parade bus gate, business district traffic management, Westgate merge signals at A58(M), Great Wilson St widening, Holbeck traffic management (Globe Road signalisation), a signage strategy and a trial closure (or access restrictions) for City Square and associated traffic management to assist buses, pedestrians and cyclists.
The aim of the scheme is to reduce traffic in City Square, enabling its transformation into a world class public space and gateway to Leeds. This includes closing the square to general traffic, reallocating road space and improving facilities for buses, pedestrians and cyclists, making the city centre a more pleasant place to live, spend time and travel through. Our proposals include changes to the square itself, as well as to Boar Lane, King Street, Wellington Street, Aire Street and Quebec Street.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund- £9.128 million
CRSTS- £2.896 million
Project Status
Activity 5 - Delivery
Consultation:
Look Back at – View our plans and have your say – Leeds City Square (commonplace.is)
Start and end dates 2016- 2024 Delivery partners
West Yorkshire Combined Authority
Other Funders
S106 - £150,000
Get in touch
Connecting Leeds reveal new plans for improving the Armley Gyratory
Last updated February 2024
- South East Bradford Access Road
-
Project overview
The South East Bradford Link Road scheme aims to provide invaluable resilience for the South Bradford highway network (and beyond). It will provide access to enable the Holme Wood housing growth area and the local enterprise zone.
This scheme aims to reduce congestion for all road users accessing South East Bradford, and parts of Leeds and Kirklees. This will also improve the reliability of public transport within the area and improve air quality.
This scheme will also unlock land for development of housing within the surrounding area and improve safety provisions for pedestrians and cyclists.
Project Lead Bradford Council District/ Area Bradford Funding West Yorkshire plus Transport Fund - £1.304 million Project Status Activity 3: Outline Business Case Start and end dates Scheme is being pipelined at the Outline Business Case stage following the November 2022 inflation review Delivery partners Bradford Council Other funders To be confirmed Get in touch Email the West Yorkshire Combined Authority Last updated September 2023
- Transformational Project Leeds Northern Outer Ring Road
-
Project overview
This project will complete a Strategic Outline Business Case to identify improvements to transform the highway network to the West and North-West of Leeds. Proposals will look to unlock a major strategic highway bottleneck caused by limited orbital highway capacity.
Proposals will include the expansion and / or upgrade of the Leeds Northern Outer Ring Road between Dawsons Corner (A647) and Horsforth Roundabout (A65).
The provision of more orbital highway capacity in this section of Leeds complements Leeds’s aspirations to reduce the volume of traffic within its urban area. It would reroute essential highway movements out of the main built up areas, providing options for efficient, congestion free and legible orbital driving routes around the city, on roads that are designed for such purposes.
Project Lead Leeds City Council District/ Area Leeds Funding West Yorkshire plus Transport Fund- £0.393 million - to develop the scheme to Strategic Outline Business Case Project Status Activity 6 - closure & review- scheme only taken to SOC Start and end dates 2019 - 2021 Delivery partners Other funders Leeds City Council- £0.100 million Get in touch Email Leeds City Council Last updated March 2024
- Transformational Project North Kirklees Orbital Route Study
-
Project overview
Funding of a Strategic Outline Business Case study to identify and evaluate options for a proposed 16.5km carriageway with an alignment proposed to follow the existing orientation of the A644 and A638 respectively and incorporate a new 9km section.
Following on from an Investment Committee workshop on 8 March 2017, it was agreed that each individual Authority would bring forward their priority transformational scheme for development. Kirklees Council have selected the North Kirklees Orbital Route as their priority scheme
The North Kirklees Orbital Route (NKOR) is a proposed road scheme that will improve access to these potential housing and business development sites, along with alleviating congestion and improving journey time reliability on a strategic transport corridor.
Furthermore, it will reduce traffic volumes along the A644 and therefore relieve congestion along the route for the neighbourhoods of Ravensthorpe and Mirfield in addition to providing an alternative route to access the M1 and M62 motorways. As a result, this will assist with the regeneration of Dewsbury by facilitating changes to its ring road in addition to assisting future developments opportunities at Cooper Bridge and Horbury Junction.
Funding has been allocated for pre-feasibility studies to identify and evaluate options.
Project Lead Kirklees Council District/ Area Kirklees Funding West Yorkshire plus Transport Fund-£283,409.00 Project Status Activity 6 - Closure and Review Start and end dates 2017 - 2021 Delivery partners West Yorkshire Combined Authority Other funders Get in touch major.transport@kirklees.gov.uk Last updated March 2024
- Transformational Project South Featherstone
-
Project overview
The Growth Deal approved West Yorkshire + Transport Fund Programme includes £12.5m allocated to the development of “transformational projects” for development work to influence government and other partners to justify future transformational investments such as rail electrification, airport access, rolling out of mass transit and preparing for HS2 and HS3.
Following on from an Investment Committee workshop on 8 March 2017, it was agreed that each individual Authority would bring forward their priority transformational scheme for development. Wakefield Council have selected South Featherstone Link Road as their priority scheme.
Funding for this scheme was allocated for a pre-feasibility study to identify and evaluate options.
A strategic case is being investigated for a series of link roads around Featherstone, Ackworth and Pontefract. A strategic outline case was prepared in December 2019 and Wakefield Council are currently progressing this scheme independently.
Project Lead Wakefield Council District/ Area Wakefield Funding West Yorkshire plus Transport Fund - £0.284 million Project Status Activity 6 - Closure and Review Start and end dates 2017 - 2021 Delivery partners West Yorkshire Combined Authority Other funders Wakefield Council Get in touch transplan@wakefield.gov.uk Last updated in March 2024
- Transformational Project York Outer Ring Road
-
Project overview
The Growth Deal approved West Yorkshire + Transport Fund Programme includes £12.5m allocated to the development of “transformational projects” for development work to influence government and other partners to justify future transformational investments such as rail electrification, airport access, rolling out of mass transit and preparing for HS2 and HS3.
Following an Investment Committee workshop on 8 March 2017, it was agreed that each individual Authority would bring forward their priority transformational scheme for development.
The A1237 is a key strategic route for east-west journeys and more northern areas of the Leeds City Region.
The upgrade of the A1237 to dual two lane all purpose (D2AP) carriageway would build on the roundabout upgrades which have already or are due to be delivered before 2021 though the WY+TF.
City of York Council are progressing on a pre-feasibility study for dualling the A1237 Outer Ring Road as their priority scheme, in order to identify and evaluate options as part of pre-feasibility development and evidence gathering for a future major project to increase the capacity of the A1237 to dual carriageway standard. The development work will include transport and economic modelling to establish the benefits of the overall scheme (and individual sections of the scheme); develop a number of detailed, costed options that provide multiple routes for further project development and delivery; based on options identified, develop a (or a number of) phasing strategy(s) for delivery; assess future network resilience that proposals would deliver; and sufficient design and investigation work to estimate the cost.
The current study is underway and a report will be produced by the end of 2018. This will consider whether all of the Outer Ring Road requires dualling and will determine the best value phasing in the short term to meet the long term aim of a better east-west strategic route.
Project Lead York Council District/ Area York Funding West Yorkshire plus Transport Fund- £0.295 million Project Status Activity 6 - Closure and Review Start and end dates 2017 - 2023
Delivery partners West Yorkshire Combined Authority Other funders None Get in touch yorr@york.gov.uk Last updated March 2024
- Urban Traffic Management Control
-
Project overview
Presently, there are four Urban Traffic Control (UTC) teams, which operate in West Yorkshire and they use various systems and technologies. Whilst the teams share resources where possible, the service levels and standards vary across boundaries, meaning it is not the most efficient use of resources.
The West Yorkshire UTMC project aims to reduce the effects of congestion and the resulting costs to the local economy.
Element A (On-street Improvements to UTC Equipment)
Improvements to facilities at key junctions and crossings on the West Yorkshire Key Route Network (KRN).
This includes the implementation of Split Cycle and Offset Optimisation Technique (SCOOT) and Microprocessor Vehicle Actuation (MOVA) and upgrading obsolete equipment.
Project Lead Leeds City Council District/ Area West Yorkshire Funding West Yorkshire plus Transport Fund-£3,993,978.00 Project Status At various stages
Start and end dates 2018- 2024 Delivery Partners Get in touch/ contact information connectingleeds@leeds.gov.uk Last updated in March 2024
Urban Traffic Management Control - Element B1
The new shared, cloud hosted UTC system will enable control and monitoring of traffic signals across all West Yorkshire districts.
Project Lead Leeds City Council District/ Area West Yorkshire Funding West Yorkshire plus Transport Fund- £1.225 million Project Status Activity 6 - Closure and Review
Start and end dates 2019-2023 Delivery partners Leeds City Council is leading on overseeing the delivery by the 5 Districts
Other funders N/A Get in touch connectingleeds@leeds.gov.uk Last updated in March 2024
Urban Traffic Management Control - Element B2
The new cloud based integrated UTMC covering Variable Message Signs (VMS), Car Park Guidance systems, Journey Time Information, Pollution Monitoring, CCTV Integration, Fault Reporting
Project Lead Leeds City Council District/ Area West Yorkshire Funding West Yorkshire plus Transport Fund- £838.000 Project Status
Activity 6 -closure & review
Start and end dates 2018- 2023 Delivery partners Other funders Get in touch connectingleeds@leeds.gov.uk Last updated March 2024
Element C
A new control centre with control room and incident space. This is capable of being used by Bus Operator representatives and as a UTC training hub and includes various upgrades to CCTV systems to increase flexibility.
The new service will provide improved day-to-day management and coordination of traffic signals across our Key Route Network and be available for use by partners e.g. bus operators, emergency services and National Highways, to improve all travel co-ordination / information.
Project Lead Leeds City Council District/ Area West Yorkshire Funding West Yorkshire plus Transport Fund- £555,000 Project Status Activity 6: Closure & Review
Start and end dates 2018- 2023 Delivery partners Leeds City Council are acting as coordinators for the 5 districts, Bradford, Calderdale, Kirklees, Leeds, Wakefield
Other funders N/A Get in touch/ contact information connectingleeds@leeds.gov.uk Last updated March 2024
- Wakefield City Centre Package
-
Project overview
Phase 1 Kirkgate
The Kirkgate Highways scheme is the first phase of the highway improvements identified for the “Wakefield City Centre Package” within the approved West Yorkshire Transport Fund scheme programme.
This scheme aims to improve connectivity within the Kirkgate area and to the rail station, attract new development to support economic growth and improve health and safety within the area.
The Chantry Road roundabout is to be improved and traffic signals are to be installed to help pedestrians and cyclists to cross safely.
By putting new infrastructure in place it is hoped this will support future development and investment in this part of the city.
Project Lead Wakefield Council District/ Area Wakefield Funding West Yorkshire plus Transport Fund- £5.5 million Project Status Complete Start and end dates Construction start May 2017 – Completion December 2019 Delivery partners None Other funders None Get in touch majorprojects@wakefield.gov.uk Last updated in February 2024
Phase 2 Ings Road
Ings Road forms part of the city centre inner ring road, to the South of the city centre, aka the “Emerald Ring”, and carries more than 23,000 vehicles a day.
It has a number of large retail developments to the south side, including Sainsbury’s superstore, Homebase, B&M Homestores and Matalan, and a need for improving the vitality of the corridor.
This scheme aims to reduce congestion and improve facilities for pedestrians and cyclists.
Project Lead Wakefield Council District/ Area Wakefield Business case summary Transport Fund updates can be found here Funding West Yorkshire plus Transport Fund- £770k Project Status Activity 2: Strategic Outline Business Case
OBC Expected in May 2024Start and end dates To be confirmed Delivery partners West Yorkshire Combined Authority Other funders None Get in touch transplan@wakefield.gov.uk Last updated February 2023
- Wakefield Eastern Relief Road
-
Project overview
The Wakefield Eastern Relief Road is a newly constructed single carriageway highway between the A638 Doncaster Road to the South and the A642 Aberford Road to the North.
It has opened up substantial job creation by providing direct access into the East Wakefield employment growth area for residents across Wakefield.
The road acts as an alternative route around the city centre and will therefore reduce congestion and increase accessibility. Providing this additional highway capacity will improve conditions for bus services, pedestrians and cyclists and open up further opportunities to provide complementary sustainable transport measures within and to the Lower Kirkgate area. It will also help to accommodate future development traffic in the East of the district.
Project Lead Wakefield Council District/ Area Wakefield Funding West Yorkshire plus Transport Fund- £37.5 million Project Status Activity 7: Monitoring and Evaluation Start and end dates 2015-2017 Delivery partners West Yorkshire Combined Authority Other funders Third Party- £14.2 million Get in touch transplan@wakefield.co.uk Last updated February 2024
- York Outer Ring Road Roundabout Improvements
-
Project overview
The YORR scheme has been the subject of a comprehensive and long term strategy to review and develop junction improvements at identified roundabouts along the A1237 York Outer Ring Road with the aim to improve strategic and local journey times on this heavily congested route. Each roundabout junction has its own challenges.
- Wetherby Road
- Monks Cross
- Haxby Road
- Strensall Road
- Wigginton Road
- Clifton Moor
- Great North Way
1) Wetherby Road was completed in early 2019 and 7) Great North Way will be progressed as a separate phase.
2) to 6) are being progressed alongside an upgrade of the Outer Ring Road to create a dual carriageway between the A19 and A64 Little Hopgrove utilising funding provided by the Department for Transport as part of the Major Road Network programme.
Project Lead York Council District/ Area York Business case summary Phase 1 Link here
Phase 2 Link here
Phase 3 Link here
Funding West Yorkshire plus Transport Fund - £37.6 million
Department for Transport MRN - £25.093 million
Project Status Phase 1 – Complete Phase 2 to 6 and dual carriageway upgrade - Outline Business Case Start and end dates 2018 - 2025 Delivery partners To be confirmed Other funders York Council Get in touch yorr@york.gov.uk Last updated Q3 2021/2022